Integration between PP module and PM module

This document explains integration between PP module and Plant Maintenance (PM) module….

 

Overview: Integration between PP and PM modules happens during following scenarios…

 

A) During Capacity Planning for work centers

B) For tracking the usage value of PRT’s

 

 

Process flow of integration during Capacity Planning for work centers:

When the production work center is overloaded with capacity, if we try to do capacity leveling and want to shift the capacity to other dates, where already some preventive maintenance activity is planned for the same work center ( equipment) during that period, then system will not allow to reschedule the production order to those days. PP Work center is Equipment in PM. In the concerned equipment’s master data you can mention the PP work centers name. This links the PP work center and PM equipment.